Islamabad Cricket Stadium Cost Jumps to Rs16.7bn — Pakistan’s Biggest Venue, 35,000 Seats
By Imran Javed | Updated: 16 November 2026 The Capital Development Authority (CDA) has finalised the revised PC-I for the Islamabad Cricket Stadium, raising the project’s estimated cost from Rs11.9 billion to Rs16.7 billion. The 35,000-seat venue, planned at the foothills of the Margalla Hills near Sector D-12, will become Pakistan’s largest cricket stadium once…
By Imran Javed | Updated: 16 November 2026
The Capital Development Authority (CDA) has finalised the revised PC-I for the Islamabad Cricket Stadium, raising the project’s estimated cost from Rs11.9 billion to Rs16.7 billion. The 35,000-seat venue, planned at the foothills of the Margalla Hills near Sector D-12, will become Pakistan’s largest cricket stadium once it is built. The revised PC-I for both phases has been completed and will soon go before the CDA Development Working Party (DWP) for approval. Construction has not started yet, but the CDA says the groundbreaking for Phase-I will be held soon and the whole project could be finished within a year.

Islamabad Cricket Stadium: Key Facts
| Detail | What is confirmed |
| Revised cost | Rs16.7 billion (up from Rs11.9 billion in the earlier, unapproved PC-I) |
| Seating capacity | 35,000 (up from 25,000) — Pakistan’s largest cricket stadium |
| Location | Foothills of the Margalla Hills, near Sector D-12, Islamabad |
| Status of PC-I | Revised PC-I for both phases finalised; to go before the CDA Development Working Party for approval |
| Phases | Two phases — Phase-I is the grey structure; Phase-II covers finishing and remaining works |
| Phase-I timeline | Groundbreaking soon; to be completed within six months |
| Whole project target | CDA aims to complete both phases within one year |
| Lowest bid | Rs8.9 billion from the Habib-ZKB-EA joint venture, later reduced to Rs8.5 billion after a Rs400 million rebate |
| Design model | Modelled on the Dubai International Cricket Stadium, according to the CDA |
| World Cup hope | PCB hopes to host some ICC Women’s T20 World Cup 2028 matches here if it is ready on time |
Why the Cost Went Up by Rs4.8 Billion
The jump from Rs11.9 billion to Rs16.7 billion is not a simple price hike. The earlier PC-I was never approved, and the revised version covers a much bigger job. When the CDA invited requests for proposals earlier this year, it decided to raise the seating capacity from 25,000 to 35,000 and to add several components that the first estimate did not include.
The revised PC-I now covers the grey structure, finishing work, lighting, heating, ventilation and air-conditioning (HVAC) systems, preparation of the ground and pitches, and a security camera system. In other words, the new figure is the cost of a finished, match-ready stadium, not just its concrete shell. That is the detail that matters most for anyone comparing the two numbers: the old Rs11.9 billion was an estimate for a smaller, partly specified project, while Rs16.7 billion is the price of the full venue as now planned.
For Islamabad, the bigger capacity is the real story. At 35,000 seats, the stadium will overtake every existing venue in the country. Lahore’s Gaddafi Stadium and Karachi’s National Stadium have long hosted Pakistan’s biggest matches; a 35,000-seat ground in the capital would give the PCB a third major venue and, just as importantly, a modern one built from scratch rather than renovated in stages.

What the Rs16.7 Billion Covers: Cost Breakdown
| Component | Amount / detail |
| Total revised cost | Rs16.7 billion (both phases) |
| Earlier estimate | Rs11.9 billion (unapproved PC-I) |
| Increase | Rs4.8 billion |
| Lowest bid (Habib-ZKB-EA) | Rs8.9 billion |
| — Stadium structure | Rs5.8 billion (three-tier stadium structure) |
| — External works | Rs3.1 billion (including 3 km of three-plus-three-lane roads and associated infrastructure) |
| Rebate agreed (Oct 2026) | Rs400 million, bringing the contract amount down to Rs8.5 billion |
| New items in revised PC-I | Grey structure, finishing, lighting, HVAC, ground and pitch preparation, security cameras |
One point needs care. The Rs8.9 billion bid — Rs5.8 billion for the structure and Rs3.1 billion for external works — was the lowest bid received for the grey structure and road network, and the Rs400 million rebate brought that contract figure down to Rs8.5 billion. That contract figure and the Rs16.7 billion PC-I are not the same thing: the PC-I is the total estimated cost of both phases, including finishing, lighting, HVAC, pitches and security systems. Readers should not confuse the two numbers, and the CDA’s own figures show the gap clearly.
Two Phases, One Year: The Timeline
The CDA is building the stadium in two phases. Phase-I covers the grey structure, and its groundbreaking will be held soon, according to a CDA officer quoted by Dawn. The bidding process for the grey structure and the road network has already been completed. Phase-I is to be completed within six months of starting.
Once the revised PC-I is approved by the Development Working Party, the CDA will start the tendering process for Phase-II, which covers the remaining facilities and finishing work. “We will try to complete both phases, covering the entire project, within one year,” another CDA officer said.
That is an ambitious target, and it is worth stating plainly: one year is the CDA’s aim, not a guaranteed completion date. Interior Minister Mohsin Naqvi recently announced at a press talk that the groundbreaking would take place within 10 days, but no exact groundbreaking date has been confirmed in the reporting so far. The modification of the PC-I, the CDA officer stressed, had nothing to do with the delay in starting construction.
| Milestone | Status / target |
| Revised PC-I finalised | Completed, 16 November 2026 |
| DWP approval | To be presented before the CDA Development Working Party soon |
| Phase-I groundbreaking | To be held soon; no exact date confirmed |
| Phase-I completion | Within six months of starting |
| Phase-II tendering | Begins after PC-I approval |
| Whole project | CDA target: complete within one year |
| ICC Women’s T20 World Cup 2028 | PCB hopes to host some matches here if the stadium is ready on time |
The D-12 Site and the Zone III Question
The stadium will stand at the foothills of the Margalla Hills near Sector D-12. It is a striking location — green hills as a backdrop, close to the city — but it is also a sensitive one. The site falls in Zone III, where construction activity is generally banned and local landowners are not allowed to build houses on their land.
The CDA’s position is that sports and recreational activities are permitted in the zone, and that a cricket stadium falls within the permitted activities. That distinction will be watched closely as construction moves ahead, because Zone III is protected precisely to keep the Margalla Hills green. For now, the CDA’s reading of the rules is what allows the project to proceed at D-12.

A Second Attempt After Shakarparian
This is not the first time a stadium has been planned for the capital. In the past, after receiving land from the CDA, the PCB began building a stadium at Shakarparian. That project was abandoned following directions from the Supreme Court. This time, the CDA itself is undertaking the construction — a change that puts the civic authority, rather than the cricket board, in charge of delivery.
The contrast matters. A project run by the CDA, with a revised PC-I going through the Development Working Party and a lowest bidder already selected, has a clearer administrative path than the earlier PCB-led attempt. Whether that translates into a stadium finished within a year is the question the next twelve months will answer.
Modelled on Dubai — and Aiming at the 2028 Women’s World Cup
According to the CDA, the stadium will be a replica of the Dubai International Cricket Stadium — the modern, floodlit venue in Dubai Sports City that has hosted Pakistan’s home matches and major tournaments. The comparison sets the design ambition: a contemporary three-tier ground with full lighting, modern dressing rooms and facilities built to international standards.

The PCB, meanwhile, has its eye on a date. A PCB official told Dawn that Pakistan is likely to host some matches of the ICC Women’s T20 World Cup 2028 at the proposed Islamabad stadium. “If the Islamabad stadium project is completed on time, we will organise some matches of the Women’s World Cup in 2028 in the capital,” the official said.
That is a hope and a target, not a confirmed deadline — the matches depend on the stadium being ready on time. But it gives the project a real sporting purpose beyond the building itself. If the ground is ready by 2028, Islamabad would host World Cup cricket for the first time. For the latest on ICC tournament plans, read our report on the ICC 2027 World Cup qualifier format. Pakistan’s recent cricket form is covered in our match reports, including India’s win over Pakistan in the Asian Games cricket final and the ongoing Bangladesh vs South Africa Test series.
What to Watch Next
Three things will show whether this project moves faster than the last attempt. First, the Development Working Party’s decision on the revised PC-I — approval unlocks Phase-II tendering. Second, the actual Phase-I groundbreaking date, which the CDA says will be held soon. Third, visible work on the D-12 site within the next few months. The cost figure is now settled at Rs16.7 billion; the test now is delivery.
Islamabad has waited years for a world-class cricket ground of its own. If the CDA’s one-year target holds, the capital could be watching international cricket under the Margalla Hills by 2027 — and possibly hosting a Women’s World Cup in 2028. If it slips, the Rs4.8 billion increase will be the first question asked. Either way, this is a project worth following closely, and we will update this story as the DWP decision and the groundbreaking are confirmed.
FAQs — Islamabad Cricket Stadium
What is the new cost of the Islamabad Cricket Stadium?
The revised PC-I puts the cost at Rs16.7 billion, up from Rs11.9 billion in the earlier, unapproved PC-I. The increase covers a bigger 35,000-seat capacity plus the grey structure, finishing, lighting, HVAC systems, ground and pitch preparation, and security cameras.
How many people will the Islamabad Cricket Stadium seat?
35,000 spectators. The earlier plan envisaged 25,000 seats, but the capacity was raised when the CDA invited requests for proposals earlier this year. At 35,000 seats it will be the largest cricket stadium in Pakistan.
Where is the Islamabad Cricket Stadium being built?
At the foothills of the Margalla Hills near Sector D-12 in Islamabad. The site falls in Zone III, where construction is generally restricted, but the CDA says sports and recreational facilities are permitted there.
When will construction of the Islamabad Cricket Stadium start?
Construction has not started yet. The CDA says the groundbreaking for Phase-I (the grey structure) will be held soon, and Phase-I will be completed within six months. No exact groundbreaking date has been confirmed.
When will the Islamabad Cricket Stadium be completed?
The CDA aims to complete the whole project — both phases — within one year. That is the authority’s target, not a guaranteed completion date. Phase-II tendering begins after the revised PC-I is approved by the CDA Development Working Party.
Will the Islamabad Cricket Stadium host the ICC Women’s T20 World Cup 2028?
That is the PCB’s hope, not a confirmed fixture. A PCB official said Pakistan is likely to host some Women’s T20 World Cup 2028 matches in Islamabad if the stadium is completed on time. The matches depend on the project finishing as planned.